Delaet’s Landing Apartments

Owner: Private

In addition to the major site work contract for the Delaet’s Landing Apartment project, was emergency change order work to relocate the 32,000 lb pressure relief valve vault. The work that was to raise the water pressure to the apartments was completed within 3 days and overcame several obstacles. The team worked late into the evening, through rain and freezing temperatures to get the job completed.